Sewer network for housing development No. 22 in In Amenas
PLASTUB supplied 704 CR8 PVC-U sewer pipes in 400 and 500 mm diameters for the first phase of housing development No. 22.
4 224
nominal m of pipe delivered
In Amenas, Illizi Province
View of In Amenas, Illizi Province.
habib kaki · CC BY 3.0Resized image
PLASTUB’s role
Pipe supply
The supply was delivered in 18 shipments. Nominal length is calculated using 6 m pipe lengths including the socket. Installed lengths are recorded on site.
CR8 pipes for the first phase of the development
Housing development No. 22 in In Amenas includes network works. The documented supply covers the sewer network. Validated shipments included 460 pipes of 500 mm and 250 of 400 mm, six of which were returned. The table shows net quantities.
- Delivery period
- 24 August – 12 November 2026
Supply details
| Outside Ø (mm) | Pipes delivered | Nominal length (m) |
|---|---|---|
| 400 | 244 | 1 464 |
| 500 | 460 | 2 760 |
| Total | 704 | 4 224 |
What to prepare for a similar project
For a housing development sewer, specify profiles between manholes, diameters and stiffness classes, burial depth and road crossings. Include the quantities required for installation.